on 10-07-2009 12:16 PM
Hello Friends,
This is regarding WBS issue.
Every WBS has a budget allocated to it and a spending limit upto 110% of the budgeted amount . However for one of the WBS we have observed that the total spending shows to have crossed 110% of the budget when we look into Expense element as well as in totality.
The budget was given at level 1 for capital and expense respectively. It would mean, the system should not allow it to exceed 110% at respective level. To check whether similar thing is happening with any other project, we quickly ran Z transaction and found that this is the only exception.
Could you please help us on this.
Thanks,
Raghav
HI Raghav,
As far as I remeber, for the budget control customizing, you can not only maintain the percent value, but also the amount. E.G. It is not allow to exceed 110 percent AND X Euros. Do you maintain such combination?
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.