Assigned budget from CJ31 and S_ALR_87013558

Former Member
0 Kudos

Hi Guys

Can you please help, Budget report: S_ALR_87013558 report WBS element assigned value is less than WBS element assigned value from Project Original budget: CJ31, S_ALR_87013558 reports display available budget of $200000 but when I create network activity for $100000 I got an error message that say Iu2019ve exceeded budget. Is there a way I can check the difference between S_ALR_87013558 and CJ31?

Regards

Sandile

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Sandile

After allocation of Budget, you also need to release the said budget via CJ32. Kindly check the same.

regards

Mitesh

Former Member
0 Kudos

Please check the report S_ALR_87013560 - Budget updates. Here you will find the budget updates that you have done for your project.

Hope this helps.