Hi Guys
Can you please help, Budget report: S_ALR_87013558 report WBS element assigned value is less than WBS element assigned value from Project Original budget: CJ31, S_ALR_87013558 reports display available budget of $200000 but when I create network activity for $100000 I got an error message that say Iu2019ve exceeded budget. Is there a way I can check the difference between S_ALR_87013558 and CJ31?
Regards
Sandile
Dear Sandile
After allocation of Budget, you also need to release the said budget via CJ32. Kindly check the same.
regards
Mitesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check the report S_ALR_87013560 - Budget updates. Here you will find the budget updates that you have done for your project.
Hope this helps.
Regards,
Ajinkya Vaidya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.