"error in activity of operation 0020 order XXXXXX" in moving DS schedule

Former Member
0 Kudos

Hello Gurus,

Just a question, I am getting error in moving schedule in DS Planning board with an error "error in activity of operation 0020 order XXXXXX". Do you knwo how to fix this and what this means.

thanks a lot!

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Wade,

Check you capacity if its over the limit (100%), you can set strategy mode to infinite scheduling then check if you still getting error while moving schedules

Former Member
0 Kudos

Hi wade-

1. If this error is coming while moving operation 20 of the order you are schduling check for PPM and resource capacity.

2. Also check scheduling strategy setting if you are considering order internal relatioship check you are not violating relationship with other operation.

Former Member
0 Kudos

Hi Wade,

1) Check the PPM/PDS data for the location product at operation 0020

whether it is maintained properly.

2) Take consistency check (individual item) in /sapapo/scc03 transaction

and check any errors are showing.

3) Check whether activitiy relationships, mode combinations are

defined correctly.

Regards

R. Senthil Mareeswaran.