Hii All

Date of services rendered by defaults is being picked from Post Goods Issue date, our requirement is to make date of services rendered equals to the actual delivery date(in our system billing date is picked from actual delivery date).

Do I need to use any user exit to do these changes or I can go in V/06 and change the pricing date as 'C' which is blank as of now.

I tried changing the V/06 to 'C' and the result was in analysis of pricing 'Services Rendered Date' was replaced by Billing date, I do not know the impact of doing the same.

If someone can throw some light on this then that will be highly appreciated

Thanks & Regards

Gaurav Manocha

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

done

Lakshmipathi
Active Contributor
0 Kudos
being picked from Post Goods Issue date, our requirement is to 
  make date of services rendered equals to the actual delivery date

Not clear on your requirement. In normal circumstances, the Actual GI date would be the billing date. Is this differs in your case ??

thanks

G. Lakshmipathi

Former Member
0 Kudos

Yes, we have customized that to actual delivery date, now we want the Service rendered date to be equal to billing date (indirectly actual delivery date).