on 10-06-2009 7:49 AM
Hi Expert,
can anybody tell me the database table, where plan and actaul cost, plan and actual revenue and budget values are stored
based on the project version group and version keys.
Thanx in adv.
Regards
Ashis
Hi,
Try tables VSRPSCO_CN, VSPRPS_CN, EVOP_VS and pass object number of WBS.
Regards,
Kabir