In report CN41N there is some columns :
Early Schd. Start B
Early Schd. Finish B
Latest Schd. Start B
Latest Schd. Finish B
Early Schd. Start F
Early Schd. Finish F
Latest Schd. Start F
Latest Schd. Finish F
Tentative Start
Tentative Finish
Tentative Duration
Tentative Work
etc...
what if B and F and how Tentative figures are put into PS?
Thanks!
b - basic
f - forecast
in planning board you can copy basic to forecast etc
network scheduling also needs to be active
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Harsh
Your question is not clear. Give more details.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
B - Basic Date
F - Forecast Date
Actual Start Date - Date on which the processing of the WBS element is started.
Tentative Actual Start date - The tentative actual start date is copied from the confirmation of activities for the WBS element.
Refer the link below;
http://help.sap.com/saphelp_erp60/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm
In that link under Dates in WBS, look on --> Copying Actual Dates from Confirmations to WBS Elements
Regards,
Kabir
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.