Hi,

In report CN41N there is some columns :

Early Schd. Start B

Early Schd. Finish B

Latest Schd. Start B

Latest Schd. Finish B

Early Schd. Start F

Early Schd. Finish F

Latest Schd. Start F

Latest Schd. Finish F

Tentative Start

Tentative Finish

Tentative Duration

Tentative Work

etc...

what if B and F and how Tentative figures are put into PS?

Thanks!

Accepted Solutions (0)

Answers (2)

Answers (2)

virendra_pal
Active Contributor
0 Kudos

b - basic

f - forecast

in planning board you can copy basic to forecast etc

network scheduling also needs to be active

Makal
Active Contributor
0 Kudos

Hi Harsh

Your question is not clear. Give more details.

Thanks

Former Member
0 Kudos

Hi,

B - Basic Date

F - Forecast Date

Actual Start Date - Date on which the processing of the WBS element is started.

Tentative Actual Start date - The tentative actual start date is copied from the confirmation of activities for the WBS element.

Refer the link below;

http://help.sap.com/saphelp_erp60/helpdata/en/c0/1885347860ea35e10000009b38f83b/frameset.htm

In that link under Dates in WBS, look on --> Copying Actual Dates from Confirmations to WBS Elements

Regards,