I see that SAP_COLLECTOR_FOR_PERFMONITOR is failing alternate hours

Please let me know of what can be the reason for the same

the job log is as folows

Job started

Step 001 started (program RSCOLL00, variant , user ID DDIC)

Clean_Plan:started by RSDBPREV

Clean_Plan:SQL statement CALL GET_DB_CONFIG failed with SQL error 99999

Clean_Plan:SQL0969N There is no message text corresponding to SQL error "-99999" in the message file on this w

Clean_Plan:orkstation. The error was returned from module "SQL08026" with original tokens

Function DB6_PM_DBCONFIG failed with return code = ADBC error

Clean_Plan:SQL statement CALL GET_DB_CONFIG failed with SQL error 99999

Clean_Plan:SQL0969N There is no message text corresponding to SQL error "-99999" in the message file on this w

Clean_Plan:orkstation. The error was returned from module "SQL08026" with original tokens

Function DB6_PM_DBCONFIG failed with return code = ADBC error

Function DB6_JOB_GET_ACTION_PATTERN failed with return code = No configuration data

Job cancelled

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Applied OSS note

anindya_bose
Active Contributor
0 Kudos

If you had refresh or system copy , then probably you have production job as well as new jobs scheduled in qty.

You can delete already scheduled job and then reschedule fresh. Check what happens.