Dear all,

I am installed ides server and also restored old backup of server but now i am going to start the sap mmc process their is disp+work.exe can not start showing status stopped (J2EE status info unavailable )but other two running perfectly.

Thanks,

Regards,

Madhu

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Check your patch level in SAP MMC by right clicking on the top level node (SID Name) and select Version Info.

Make sure the same patch level for disp+work.exe is the same as the patch level of the other components.

Former Member
0 Kudos

hi,

If the disp+work.exe for J2ee is not running, from my previous experiences , it was the following parameters

-Xms1024m

-Djco.jarm=1

-XX:PermSize=256m

-XX:MaxPermSize=256m

-XX:NewSize=171m

-XX:MaxNewSize=171m

I would set up teh value as above , wht configuration the system would be and the SAP would come up

then i tune the parameters

Former Member
0 Kudos

Do you know what was the kernel patclevel before .Please go with the kernel upgrade.Rememebr to take the backup of the old kernel.

First check dev_disp logs .

check thet the database is running.r3trans -d and chekc that there is no return code.

thanks

rishi abrol