Dear all
The problem statement is as follows
I am running a linear optimizer with fiscal buckets of
1-5
6-20
21-31
for a month. all the orders created sit in the beginning of the bucket. After that we are running a capacity levelling.
ALL days are working days for resources. Strangely a pattern is observed
on
2,7,22 the resource capacity is 0% utilised. i.e the next day of the start of the optimisation bucket.
I am doing leveling in the daily bucket
THe GR resource is also all days working.
IN the capacity view there is 18 hours of capcity available still no orders are getting leveled for 2,7,and 22.
I am using forward scheduling, the pattern is as below, i have raise an OSS but just wanted to check if there are chances of a
functional slip out.
Date Before After
1 500 100
2 0 0
3 0 100
4 0 100
5 0 100
6 1500 100
7 0 0
-Regards
VIrender
Hi Virender,
We were getting the same problem that is because of the Time zones.
Please check note 1395075.
This will help you.
Regards,
Kishore reddy.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.