We are configuring SAP ChaRM in our Landscape and when we execute the Normal correction scenario
We got a message that NOT ALL TEST TRANSPORTS HAVE BEEN IMPORTED and Status was reset by system Message no. SOCM_ACTION_LOG097
Hi,
You need to check your maintenance cycle.
Also the transport of copies is correctly imported in qua? Per each TR there must be at least one transport of copies transport
request created, can you ensure this TOC is also imported, this is the most common error.
Regards,
Shyam