on 10-01-2009 12:05 PM
Hi All,
In Project Builder CJ20N, I create a Project Team for the WBS Element.
Once I assign a new person, system is not allowing me to change the relationship date.
Does anyone has any ideas as to how to do this??
Regards
SK
There is another way of doing it.
There is an icon called "MOVE" through which you can change the dates for the resource.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
once you create the relationship date then you cannot change
you need to delimit the dates and create new assignment
in CJ20N select WBS
Edit -> WBS - project team
expand and place cursor on the person assignment
go to menu path
Assignment -> Delimit#
click on delimitation date enter the new end date, then click on delimit
this new date is the end date
if you need to extend the person then create a new assignment
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
Please check if CMP2 can give you the possiblility.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.