cancel
Showing results for 
Search instead for 
Did you mean: 

SAP PM:Schedule Maintenance Plan

Former Member
0 Kudos

Dear Sir,

How can I release call in Schedule maintenance plan(IP10) & what are the use of start option? However, maintenance plan has been scheduled on plan date.

Regards,

Akhilesh

SAP PM Consultant

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

While scheduling the maintenance plan using IP10,The use of start option is to specify Date on which the entire maintenance plan should start . The other options available to schedule the maintenance plan is by manual call you can always use that option to forcefully call the plan without altering the maintenance plan......

Nikhil

former_member187991
Active Contributor
0 Kudos

hi

System will automatically release the call object when the counter or time has reached as per the cycle time .

Strart option is useful from which the maintenance plan schedule to be started.

regards

thyagarajan

Former Member
0 Kudos

Hi,

Use IP30 Monitoring function(Job).