Is it possible that system can calculate or update the activity forecost date when i confirm the activity, Senerio is that when i confirm the activity with degree of progress then system will calculate the actual remmening work, I need to estimate the activity forecast date by actual remmening work when i confirm the activiy

thnks

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi sahmad_77,

There is enhancement CONFPS01, which enable the program to set default value, e.g. forecast date based on your own logic.

Please implement the corresponding user-exit EXIT_SAPLCORF_006.

Kind regards,

Zhenbo