on 10-01-2009 6:32 AM
Dear Experts,
We have defined dynamic modification rule for a material at MIC level. There are totally 10 MICs . For the first inspection lot of this material this three MICs to be inspected . Then for the next 14 lots these MICs to be skipped from inspection .
Then for the sixteenth inspection lot these three MICs to be inspected. But system is skipping the sixteenth lot also. Please explain why it is happenening and what has to be done.
Hi,
Pl check the skip stage in which check the number of skips. It should be 15.
Thanks,
Anil