FB50

Former Member
0 Kudos

Hi Friends,

While posting through FB50 in the WBS element field column we put WBS element, now my question is what is the required condition forthat WBS like

a) If it must be in released status

b)the activity must belong to that WBS and must be in confirm status.

Any pointers

Regards

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Yes WBSE should be in REL status, in order to post cost. since you are posting cost to WBSE, you dont have to worry about activities assigned to that WBSE.