on 09-29-2009 10:40 AM
Dear All
What is RRB and how can we use in PS for Generating the invoices Link with the SD
Regards
RAJ
Hi,
Kindly go through the details provided in below mentioned link:
http://help.sap.com/saphelp_46c/helpdata/en/59/54fc37004d0a1ee10000009b38f8cf/frameset.htm
I hope it would be helpful to you.
Regards
Avisek BhardwajI
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
RRB is done for projects for billing the customer based on the actual work done / resources utilised. Here you will not have any fixed prices as done for Milestone billing.
You bill the customer based on the actual cost or expenses spent on the project.
For e.g. you can bill the customer based on the actual resources utilized in carrying out a particular task or activities of the project based on maintained activity rates.
1.RRB can be done using DP91 for which you need to configure DIP profile in ODP1.
2. Input the WBS in account assignment TAB in Sales order and DIP profile in SALES B TAB
Follow the link for more details;
http://help.sap.com/saphelp_erp60_sp/helpdata/en/4a/ac853478616434e10000009b38f83b/frameset.htm
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.