Resource Related Billing

Former Member
0 Kudos

Dear All

What is RRB and how can we use in PS for Generating the invoices Link with the SD

Regards

RAJ

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Kindly go through the details provided in below mentioned link:

http://help.sap.com/saphelp_46c/helpdata/en/59/54fc37004d0a1ee10000009b38f8cf/frameset.htm

I hope it would be helpful to you.

Regards

Avisek BhardwajI

Former Member
0 Kudos

Hi,

RRB is done for projects for billing the customer based on the actual work done / resources utilised. Here you will not have any fixed prices as done for Milestone billing.

You bill the customer based on the actual cost or expenses spent on the project.

For e.g. you can bill the customer based on the actual resources utilized in carrying out a particular task or activities of the project based on maintained activity rates.

1.RRB can be done using DP91 for which you need to configure DIP profile in ODP1.

2. Input the WBS in account assignment TAB in Sales order and DIP profile in SALES B TAB

Follow the link for more details;

http://help.sap.com/saphelp_erp60_sp/helpdata/en/4a/ac853478616434e10000009b38f83b/frameset.htm

Regards,

Kabir