Valuation with material cost estimate: error with product "FTSH03030061"

Dear Friends:

In VF02, Change Billing Document,No was entered and I selected Release to Accounting. I get the following Error.

Valuation with material cost estimate: error with product "FTSH03030061"

Message no. KE350

Diagnosis

In Profitability Analysis (CO-PA), the system tried to valuate a line item using the current standard cost estimate.

In order to determine the current plan period, the system needs to read the valuation segment of the material master.

The system has found that the current plan period is not filled for product "FTSH03030061" in plant "1300".

The system looked for the material cost estimate using costing key "Z01", as defined in the Customizing settings for CO-PA

Display material (View: Costing)

How to overcome the error? Please advise.

Regards

MSReddy