on 09-28-2009 7:09 PM
Hi Everyone,
I want to be able to use costs in PDS.
The follwoign OSS notes# 993080 describes a report to maintain the costs. can someone explain me how it can be done and what are the additonal details to be included in the BADI for me to be able to maintain the costs. Thank you
Regards
Akshay
Hi Akshay,
The very simple way to maintain costs at PDS is
that you use transaction PDS_MAINT in R/3 and
maintain all the relevant costs in the PDS structure
Once it is maintained, use transaction
CURTO_CREATE to transfer these costs to APO.
Please confirm whether this will work for you.
to resolve your problem
Regards
R. Senthil Mareeswaran.