Dear All ,

Our client does not want to maintain Q info reccord through QM procurement activation . However He just wants to ensure that the invoice is blocked if quality has not released the materials .is this posible in standard SAP ?

Kindly let me know .

Ram~

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

if you want to put Ennhancement during MIRO then it possible through block MIRO before UD posting is LMR1M001

check this.....but remember this works only in MIRO tcode.

for more details

Regards

Sujit