on 09-24-2009 12:42 PM
Dear Experts,
We are working in SRM 7.0 Classic scenario.
In carry out sourcing when we try to create a contract, contract is not created and transfered to backend.
But if we select Purchase Order in carry out sourcing we can able to create and the document is transfered to Backend.
Is there are any specific configuration such as ipc or badi has to be implimented.
Kindly give your responce.
Thanks in advance.
Regards,
B.N.Karthikeyan
Hello Karthik,
The BLAORD and BLAOCH message types are defined for distributing contracts. The BLAORD message type is used to create a new contract and the BLAOCH message type is used to change an existing contract. The BLAORD02 IDoc type is used for the message types.
also Check this out...
Arshad
Edited by: arshad ahmed on Sep 25, 2009 12:28 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Are you using Central contract Management? If yes, please check the back end ERP6.0 EhP4 activated or not. Also please check the PI service have been activated properly for contract data exchange
Pls let me know the result
Thanks
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
U need to add message types BLAORD & cond_a in ECC & conidtions types of ECC & SRM has to be same.
Regards,
NNK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.