Hi Experts,
When I create a NB PO with a requested delivery date of 06.10.2009 and I entered a planned delivery time of 3 days.
In the delivery(NLCC), all dates are set to 06.10.2009 when only the delivery date should have this date => Planned GI date, Material availability date... should be retro calculated with the routes and set on 02.10.2009.
Kindly suggest.
Hi,
Check if you have the setting for the determination of the route with tcode SM34 for VC_TROLZ.
Regards,
Eduardo