on 09-24-2009 2:41 AM
Hi,
I was running transaction CM25 and despatching the planned orders.
I got the error message below and the planned order weren't despactched.
Message no. CY831 - Dispatching sequence: Structure KBED is not currently supported
Any idea why this happen and how to fix?
Thanks,
Thomas
Dear,
I hope u have activated capacity availabilty check & assigned overall profile at OPJK.
In the time profile of the overall profile, you define the planning period in which the system searches during finite scheduling for dates with sufficient capacity.
In the strategy profile of the overall profile, you define the planning direction in which the system searches for dates with sufficient capacity.and make sure is that assigned in production scheduling profile tcode OPKP
Please refer SAP Note 204841 and 334455 - Message CY831 Structure KBED is not currently supported
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Brahmankar,
many thanks for your suggestions.
We're upgrading from 4.5 to ECC6.
I have checked and kept the configurations the same.
We get the same error in 4.5, but the planned order can still be dispatched.
In ECC6, the planned order is not dispatched.
The data are exactly the same between 4.5 and ECC6.
Any idea what's missing?
Thanks,
Thomas
Dear,
You have to use transaction OPPQ to maintain the plant parameters. Here you can maintain the conversion from planned order to production order.
Maintaining this parameter actually allows you to dispatch planned orders (without converting to production order.
Please refer this link also,
Regards,
R.Brahmankar