Hi
My requirement is to transfer material from plant to plant. STR will be created via MRP. My question how do I carry out ATP for material availability at source plant?
Hi
My question how do I carry out ATP for material availability at source plant?
For this a standard setting is available in STO s basic configuration
img-materials management-purchasing-purchase order----set up stock transport order
In this there is a setting available that assign delivery type and checking rule to the plant
That checking rule is availablity check's checking rule We can assign B there that is SD delivery
Checking group will be there in MMR say for example 01
For this combination that is 01 and B we have to maintain control parameters in OVZ9
Right now i am not infront of SAP screen
While creating PO itself in ME21N system performs availablity check automatically
You see can see this in status bar when the material is entered and all the other details are entered as a message availablity check being carried out
From the menu bar on the top in the PO screen we can scroll thro and find out with what control parameters system has performed availablity check
What is STR?
Regards
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.