on 09-23-2009 11:39 AM
Hi
How can you transfer Purchase Requisition with release stragety to SRM generally ?
Regards
Alexander
Hi Alex
you must release the PR then only eprofile will be set up in EBAN table and this pr will sit in EPRTRANS table. As you aware from eprtrans table you can pull into SRM by req transfer job and in SRM cart will be created with approved status.
br
muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There is no such option in SRM
In ECC6.0 you have to create P.R with Release strategy . Release the P.R in ECC6.0
Following tables to be updated in ECC 6.0
Table: V_T160PR -For the Purchase Group
Table: V_T160EX - for the purchase group and material group
Run the report : BBP_EXTREQ_TRANSFER
then the P.R in ECC 6.0 will be transferred to SRM
Create the shopping cart in SRM which is subjected to APPROVAL PROCESS (like Release stragery in ECC 6.0 )
then P.O is created either in SRM server(OR) backend ECC 6.0
Regards
G.Ganesh Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.