while creating the networks under WBS it's giving error

Former Member
0 Kudos

Hi experts,

i am not able to create the network under WBS element. while creating the Networks it's asking Scheduling type under scheluling tab. I tryed giving with backwards and forwards options, after press the enter it's says"The factory calendar does not exist (contact system administrator)". I am facing this error..

Could anyone please help on this....

Many Thanks in advance

Srinivas

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Have you tried giving factory calendar in project definition or under dates tab of WBS?

Regards!

Former Member
0 Kudos

Hi thanks for quick reply...I assigned factory calender 01 in Project definition as well as WBS element(under dates tab).

But it's giving the above error..

best regards,

srinivas

Former Member
0 Kudos

Did you check the factory calendar maintained for the plant as mentioned above for the particular Network type?

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check if you have maintained a factory calendar in the following;

1. OPSA - For project profile

2. SPRO --> Enterprise structure --> Defintion -> Logistics General -> Define, Copy, Check plant. Check the factory calendar for the plant.

Ensure the calendar is created and defined in your system.

Also, maintain scheduling type in OPU6 T-code for the network.