on 09-23-2009 7:34 AM
Hi experts,
i am not able to create the network under WBS element. while creating the Networks it's asking Scheduling type under scheluling tab. I tryed giving with backwards and forwards options, after press the enter it's says"The factory calendar does not exist (contact system administrator)". I am facing this error..
Could anyone please help on this....
Many Thanks in advance
Srinivas
Hi,
Have you tried giving factory calendar in project definition or under dates tab of WBS?
Regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check if you have maintained a factory calendar in the following;
1. OPSA - For project profile
2. SPRO --> Enterprise structure --> Defintion -> Logistics General -> Define, Copy, Check plant. Check the factory calendar for the plant.
Ensure the calendar is created and defined in your system.
Also, maintain scheduling type in OPU6 T-code for the network.
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.