Hi,

We are planning for SAP upgrade in our Production environment and we are facing the below listed constraints and need your advice on the options to peform ECC Upgrade.

1) Present HW resource is already facing bottleneck and so no additional load can be added.

2) We have a completely new HW environment due to which we are unable to perform the test upgrade.

Also, is there anyway to perform the Prepare Activities on new hardware (copy of Production system) first and then do the delta data migration for update of transactional data from present production system to new system (Prepare Activities done on this system) without affecting the Prepare Activities data.

Thanks & Regards

Pratap

Accepted Solutions (0)

Answers (1)

Answers (1)

markus_doehr2
Active Contributor
0 Kudos

> Also, is there anyway to perform the Prepare Activities on new hardware (copy of Production system) first and then do the delta data migration for update of transactional data from present production system to new system (Prepare Activities done on this system) without affecting the Prepare Activities data.

No.

I wonder why you just don't a system copy (backup/restore) to the target system and start the upgrade there?