How to stop PP/DS order (when sent to R3) from re scheduling

Former Member
0 Kudos

Hi All,

Currently when we send PP/DS order to R/3, the order is re scheduled. As a result we get different dates from what we have in APO.

Is there a way to turn of f the rescheduling in R/3 and keep dates the same as it comes from APO.

Regards

MA

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Mahmood

Rescheduling normally happens in ECC when the master data of APO and ECC are not matching. The primary suspect in this case is normally the Resource/Workcenre. Pls check if the capacities mapped in APO and ECC are same during planning and Sending of the data ( in case ur using collect change pointers). The best would be if you use external capacity in the resource which will pick the existing capacities during the planning of resources and will not lead to any rescheduling because of resource availability.

Do let me know if it helps you.

Regards

Virender

Former Member
0 Kudos

Found that with /SAPAPO/CP3 t code set to no re transfer, this can be resolved.

Former Member
0 Kudos

Hi Mahmood,

In APO customisation, under object specific settings for

publication, check the retransfer field how it is maintained

Regards

R. Senthil Mareeswaran.