Is there any as on date report in PS for actual cost of a project i.e,Actual cost upto a particular date.

Thanks in advance

Regards

Abhijit Sen

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Edited by: SWAPNIL PRAMOD KHARUL on Sep 21, 2009 7:40 AM

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi

Edited by: SWAPNIL PRAMOD KHARUL on Sep 21, 2009 7:40 AM

Former Member
0 Kudos

Hi

You can use CJI3-Display Actual Cost/Revenue Line Items Report for particular Posting Period.

Swapnil Kharul

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

You can get it from CJI3 report.

There will be 2 fields for posting date : 'From' and 'To'.

Input the required date in the Posting date 'To' field.

regards,

Amol

Former Member
0 Kudos

Hi,

Check these Reports for Actual project cost;

CJI3

S_ALR_87013531

Regards,

Kabir