Hi,
When I run SNP heuristic it is gentrating PR as STR(shown in key figure STR in Planing book) Purchase requisition has source of supply indicating vendor location but at vendor location Preqrel is not visible.
We are usig subcontracting with source location
Strange thing is behaviour is correct for demands in PPDS horizon I mean for PPDS purchase requisition there is no problem
Please note we checked following things-:
1. Product is available at both plant and vendor location
2. SNP PDS is available and valid at vendor location.
3. Trasportation lane with external procurement relationship of type subcontracting(from R/3 purchase info record) is available.
4. External procurement relationship is valid and active.
can anybody suggest how to resolve this?
Siddharth.
Hi,
Planning book we are using is copy of standarad planning book mentioned by you. Still to reconfirm I checked by running heuristic in standarad planning book but still receipt element comes in key figure distrubution receipt planned and not subcon.
Please suggest
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The receipt element should come in the subcon one...
Please check that your lane has a means of transport (the means of transport is not created automatically, you need to add it manually)
If your lane is complete: try to create an order manually in the K fig Distribution Receipt (Subcontracting Planned) from your target location.
This should create automatically production planned (subcontracting) on your subcon vendor.
Regards
Julien
Hi,
Problem is resolved by maintaining mode of transport and running heuristic again.
Thanks very much for your time and valuable inputs.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There is no mode of transport maintained but it is some of other locations also where we are getting correct result. Still I will check by maintaining mode of transport if problem gets solved and get back in case of any problems.
Regards,
Siddharth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siddharth,
Did you run the heuristic in the 9ASNPSBC planning book? (or a copy of it)
You need the key figures Distribution Receipt (Subcontracting Planned) / Distribution Demand (Subcontracting) / Production (Subcontracting Planned) ((or Kfig with key figure functions 4015 / 4016 / 2005)... and the proper macros.
Thanks and Regards
Julien
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.