on 09-19-2009 8:48 AM
Hi All,
When i entered requirement from CJ20N, its creating Reservation as well as PR. So that After GR is done i can issue the material against that resn #. If i create a PR manually using acc ass cat as Q using WBS element, its not creating any reservation No. Then how i can issue the materials ?
regds,
CB
creat reservation no. -
mb21
enter
1 mvt type -
221 for wbs
2 plant
now execute it.
after executeing , enter the wbs element no against which you had created PR
enter material no , qty & save.
reservation no is created
regards
pari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
To create Material PR on Network Activities, select Prelim- Reuirement for WBS Element from standard pop-up in Network Transactions and to create material Reservation select Reservation for Network from Popup
Hope this will help you
Swapnil Kharul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can create manual reservation using Tcode MB21 for that WBS and then issue that material against this reservation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.