cancel
Showing results for 
Search instead for 
Did you mean: 

IS-Mill: Multiple-Output Planning (MOP)

Former Member
0 Kudos

Hi,

I want to use Multiple-Output Planning functionality of DIMP (IS Mill).

For that which all Systems are required apert from SAP ECC IS-Mill? Can I use MOP functionality without having SCM (APO)?

Can you share any document link which clarifies this query?

Regards,

Abir.

Accepted Solutions (1)

Accepted Solutions (1)

michael_franz
Explorer
0 Kudos

Hi Abir,

the Multiple-Output Planning functionality of DIMP requires APO.

Here you can find information about the minimum release requirements:

[http://help.sap.com/saphelp_scm41/helpdata/en/79/181EC440494340863EEC7460624D44/content.htm]

Further details about the functionality are here:

[http://service.sap.com/ibc]

=> Industry Solutions

-> SAP for Mill Products

-> Multiple Output Planning

->Business Scenario Description

->Business Scenario Configuration Guide

You can access the configuratio guide of the scenario directly here:

[http://help.sap.com/saphelp_scm41/helpdata/en/82/0d8a3ef3ecc478e10000000a114084/frameset.htm]

Kind Regards

Michael Franz

Solution Management

IBU Mill Products & Mining

IS Manufacturing Industries

SAP AG

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

What Industry do you intend to use this ?

Thanks,

Sandeep Mondkar

SCM - CDP Consultant