Which Requirement type w/o ATP and special Stock u201CEu201D

Former Member
0 Kudos

Hello Experts,

There are 2 Requirements types used in a company:

1st u2013 KSV Sales order with consumption

2nd u2013 KEB Individual cust. purchase ord.

Which strategy will skip stock quantity during ATP check? I donu2019t want to use special stock u201CEu201D - Orders on hand.

After saving sales order, system should create planned production order.

I think KSV, and KEB can not be used, because: KSV u2013 will always check ATP; KEB u2013 will always use special stock u201CEu201D.

Please give me some advice which requirement type should be used in this case?

Could you also tell me the difference between all those different Requirements types.

Thanks,

Maciej

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Use strategy 81 / KMSE

thanks

G. Lakshmipathi

Former Member
0 Kudos

Thanks for your answer.

Requirement type KMSE - Assembly planned order is assigned to Requirement class 200 - Assembly: plnd order.

Requirement class 200 has Special Stock Indicator "E".

After production, materials will be seen on special stock "E" and I would like them like in Requirement KSV (with out any special stock).