Hi!

Can we get the estimate auto matically the resource as per the duration planned in PS. I dont want to change the no. of resources required at activity level.

Regards

Bekele

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Step1: Tcode CJ20n

Step2: Select the activity for which you are interested in

Ste3: Go to the internal tab and mention 3 Calculate number of Capacities in Calculation key.

Step4: Enter and Save.

Alternatively it can be defaulted from Tcode OPUU. (Activities Tab >Internally Processed Activity>Calculation Key-->3)

Hope it helps...

Thanks!!!

Answers (1)

Answers (1)

MohanDesai
Active Participant
0 Kudos

Thanks