on 09-18-2009 5:34 AM
Hi!
Can we get the estimate auto matically the resource as per the duration planned in PS. I dont want to change the no. of resources required at activity level.
Regards
Bekele
Hi,
Step1: Tcode CJ20n
Step2: Select the activity for which you are interested in
Ste3: Go to the internal tab and mention 3 Calculate number of Capacities in Calculation key.
Step4: Enter and Save.
Alternatively it can be defaulted from Tcode OPUU. (Activities Tab >Internally Processed Activity>Calculation Key-->3)
Hope it helps...