on 09-18-2009 12:21 AM
Hi Experts,
I just want to ask if in case I manually enter a production order quantity for a certain material location in Production(Confirmed) key figure, would it automatically populate dependent demand quantity on components?
I understand that if production order comes from SAP R/3 and CIF to APO, I will have both production order and dependent demand in palnnign book. But in case production order is loaded from an external file or manually entered, would it also gives me dependent demand? Thanks.
Regards,
Mylene
Hi Mylene,
As you have rightly said, SNP will plan planned orders and production orders
will be created and confirmed based on the availability of raw materials and
componennt items.
Production confirmed is based on the availability of receipts.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
OOps didnt see the last post,
The orders that you create in APO are planned orders and the ones ur getting from ECC are production orders maybe thats why the ATP categoryis different. The production orders which will come from ECC will also have the dependent data populated. kindly cif the orders to APO and see , The dependent demand will definitely be populated.
BTW: Thanks for the compliment Julien ...
-Regards
Virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Meylene
If you just wanna see the creation of dependent demand on [unch of planned orders you can do that in Product view. Do as mentioned below
1. In Product master for which you want to create a production confirmed put PPDS horizon in PPDS tab. lets say 15 days.
2. Open Transaction /sapapo/rrp3.
3. Punch an order inside PPDS horizon of some qty and put date. ( pre requisite: PPDS PPM should exist)
4. save and come out
The punched planned orders will appear in the production confirmed key figure of ur planning book
and you will be able to see the dependent demand for the input materials.
Hope this will help you test your case.
-Regards
Virender S Thakur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
followup
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey Mylene
I know the query has been answered but i beg to differ from what people are suggesting in the above mentioned arguments. If tyou are getting orders from an external system it will definitely come to APO and re-explode the BOM with the given data it is bringing in. The dependent demand will be automatically populated as to make a Production confirmed there are certain pre-requisite for the system. In case you are getting it from a different ERP system itself, you might be using a template PPM or certain functional modules to create a Production confirmed in the system. It will definitely re-explode the BOM and dependent dependent demand will be automatically generated.
DO let me know if what i suggest is right.
-Regards
Virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virender,
Thanks for your answer.
The problem is i dont know how I can test since I can not change this key figure to be editable and then manually entered some value on production(confirmed) so I will see if it will generate dependent demand. We are still in the design phase so we dont have the non SAP to SAP interface yet.
I hope someone could give me an idea how to test this scenario. Thanks
Mylene
Hi Mylene,
I agree with Virender (who seems right quite often actually )
I think you are approaching this the wrong way: you cannot create a SNP production confirm; and will never be able to...
However, you can create a produciton confirm order via interface; and , providing you do that properly, your order will be visible in SNP, both in produciton confirm and dependant demand.
I hope it make sense.
Where you need to concentrate your effort is on this interface.
You will probalby need interface to create PDS / PPM and to create comfirm order.
I am not an expert here, but I guess the best is to use bapi (e.g "PrdDataStructureAPS" (BUS10014) or "ProdProcessModelAPS" (BUS10003 / "ManufactOrderAPS" (BUS10503)
Thnaks and Regards
Julien
Hi again,
I tried creating an order from product view and it put an entry in production(confirmed) keyfigure. It populate the dependent demand but my concern is the ATP category which was assigned to my order was not the same acategory as when I am getting it through CIF. is this ok?
Sorry as I am not yet clear on how and what category will be created based on what was maintained in key figure in planning area.
Thanks for your help.
Mylene
Hi Mylene,
SNP heuristic does not populate the production confirmed values.
Production confirmed values will get populated based on the
confirmation of receipts at the R/3 side (execution side) which
includes available stocks.
These available stocks will be used by SNP during deployment
and heuristic for deploying the stocks.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Senthil,
Thank you again for your reply.
So this means that in case we will get the production(confirmed) quantity from a non-SAP system, we will need to get/post corresponding dependent demand for that since APO SNP will not do this for us?
APO SNP will only do this for production(planned) -- dependent demand transactional data.
Thanks.
Mylene
followup question needed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks to all your reply
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mylene,
Until you carry out planning run, you cannot get dependent demand for
its components. As your production order is confirmed, it will not get
deleted by planning run and its dependnet demand will get planned.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I dont think you can make the KF Production(confirmed) as input and enter a value there. Anyways to my knowledge the dependent demand wont get automatically if you enter a value for Production(confirmed), as there is no BoM explosion happening.
Regards,
Senthilrajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
4 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.