GTS is connected to two distinct feeder systems (A and B). Basis team plans a refresh (homogenous) of A-PRD down to A-QA on the first of the month. They will also perform the same refresh strategy from GTS-PRD to GTS-QA and then re-establish the logical system namings so that the new copies in the QA environment can recognize each other. However, they are not performing a system refresh from the B-PRD down to the B-QA environment. We are concerned that the refreshed copy of GTS-QA will no longer recognize the B-QA records.
Has anyone any experience with this situation, and what can be done to avoid problems?
Thanks in advance for your help!
-Greg
Greg,
You are correct. The GTS-QA will no longer recognize both A-QA and B-QA the moment it is refreshed with GTS-PRD.
My Question is when they are re-establishing the logical system setting etc., for A-QA on newly refreshed GTS-QA, what is preventing them for not adding the same settings for B-QA?
Regards,
Satya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.