Hi Guys,
I have few queries pl help me to solve it.
1. How to make one r/3 resource as calendar resource in APO?
2. Can we use multi calendar resource in PPM?
3. When i convert PPDS PPM to SNP PPM i am getting error operation have SNP relevant and Non SNP relevat data , is it anything to do with multi calendar resource?
4.When converting PPDS PPM to SNP PPM i am getting error COM routing using application program ,.how to resolve this
Please clarify this.
Thanks and regards
Thamizh
Hi,
May I know for what purose you need calender resource in R/3.
Goods receipt processing time in R/3 will be represented in APO by activity with calender resource if calender resource is assigned to location(plant) as inbound resource.
It does has any capacity consumption so I donot think it can be mixed resource.
Regards,
Siddharth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thamizh,
Hopefully some of these will help you a bit...
1. You can either define the setting globally (CFC9) or in the work center iteself.
Go to work center capacity header > APO resource > define the resource type and category
If you want to use in SNP, ensure you create a "mixed" resource.
2. There is no capacity consumption for calendar resource, I don't really know why you will need a multi resrouce here.
3. Check if your resource as been flag as non SAP relevant (again in work center ...- > APO resource)
4. Do you have the error number and description? You can open an OSS... they will help here
Regards
Julien
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.