Dear All.

Is it possible to set SolMan ChRM in the way, that specific user will work with activity change request or corrections (urg. or normal) or even Adm. M. in specific maintenance cyclus. That means, one user could work another not.

Regards,

Petr

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Refer the note 881553 for the roles and authorization objects for Charm.

Spefically you need to maintain the authorization object CRM_ORD_PR

regards

Naveen

Former Member
0 Kudos

Dear Naveen.

So as I understand well I have to assing authorisation object S_PROJ_GEN with the value = "project name" and than the user can asign only allowed project. But what about other activities such as corrections. Can I say that this correction belongs to this project and thus this user can or cannnot work with this activity?

Thank you for your help.

Petr Syka