Former Member
0 Kudos

Hello PS Experts,

We do Progress analysis and update the Progress Tab of activity in

CJ20N. One of our business requirement is to make one of the fields in

Progress Tab as required field.Eg. Progress Version.

Is there any way to make this field as required ?

Thanks in advance

pscosnultant

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Take Help of the ABAPer.

Step1: Tcode SHD0

Step2: Enter: Transaction Code: CJ20N,

Screen Variants Tab

a) Screen variant: ZCJ20N

b) Program: SAPLCNEV_06_DIALOG

c) 200

Step3:Hit F5, Go to the Progress Tab and Later double click on the Progress Version. Another window will pop up, please make the desired fields as required.

Step4: Exit and Save.

Hope it helps...

Thanks!!!

Former Member
0 Kudos

Hi,

Go with the method Varshal told, it works perfectly well.

Thanks! i also needed it.

Former Member
0 Kudos

Hi Varshal,

Thanks for your input. Does this applicable to only one project or whole CJ20N?

As I mentioned ,my requirement is to make one of the fields in Progress Tab in Activity or Activity Element as required field .

Also I do have different projects. I would like to restrict it for some projects only based on Project profile or network profile

Thanks Again

psconsultant

Edited by: psconsultant on Sep 16, 2009 1:42 PM

varshal_kachole3
Active Contributor
0 Kudos

Hi,

This changes will affect all the Projects being created in future.

Hope it helps...

Thanks!!!

Former Member
0 Kudos

Hi,

Very Good. Is any way to restict this with Network Profile or Project profile.

I don't this happening across all the projects I have.

Thanks again

pscosnultant

Former Member
0 Kudos

Hi ,,

I just tried and doesn't seems working for me.

I checked the progress version and measurement method as required field and saved.

Then created new Project too. But the fields under progress tab is still not reuired field.

Thanks

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Once you Save and Exit.

Step1: Save the CHNAGE TRANSCATION VARIANT screen and press enter twice. system generate the transport request.

Step2: Run the transcation SHD0 click on the standard variants TAB and click on the activate button.

Hope it helps...

Thanks!!!

Former Member
0 Kudos

Hello,

Litle confused here. In the first section you mentioned to create screen variant and second section you are mentioning to change the transaction variant.

Can you please explain me in details. Please.

Former Member
0 Kudos

Hi PC

can you please explain how did you achieve this requirement. i have a same requirement.

former_member210673
Participant
0 Kudos

Varshal,

How did you figure the program that needs to be used?.

-thanks

Former Member
0 Kudos

Hi We can write a validation for making thses fields required using as work around. You can create validation in tcode OPSI and write your own exit for and check the fileds using FM 'CNEV_05_GET_OBJECT_PARAMETERS'. This validation can be assigned to project profile for which this chekc to be applied.

in exit you can check if LT_EVOP is initial then give error message.

Answers (2)

Answers (2)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi Harsh,

Thanks for the reply. These fields doesn't come under OPUC

Thanks

ps