Hello Gurus,
Can anyone please suggest me tables from where I will be able to derive the following:-
a) Budget at the WBS level 2
b) The budgeted hrly rate
c) Actual Hrs booked to the WBS level2
d) Actual hrly rate to be charged to actual hrs booked.
It would be nice if someone can provide me with this information.
Hi
I think you cannot directly get these values. You may use the below tables.
(1) BPIG for Budgets. In this look for Object No. relevant for WBS i.e PR000....
(2) For Actual Cost look in COEP tables
Hope it helps
Regards
Babu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check Table BPJA and BPEG for Budget.
For Actuals check RPSCO.
Regards,
Nitin Ghadge
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
budget table is BPJA for transaction KBUD for object PR*, get WBS number and Object numbe relationship from table PRPS
for costs RPSCO
not sure about budgeted rate this should be plan values
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.