on 09-15-2009 8:19 AM
Hi
I am in process of making out road map for integration of SAP-PS and Primavera in my company.
The Business scenario is such that the third party contractor provides all the Turn key services in form of material & services to do designing, procurement, erection of equipments and commissioning.
Contractor is working on Primavera and provides his reports in Primavera only.
Management wants to PS-Primavera integration to transfer structure (including activities), dates, capacities from Contractor's reports to our system and any subsequent changes proposed by management needs to be given back to contractor.
I will request any person who has experience in PS- Primavera integration to comment on the following:
1. What tool (third party interface) is best available in the market to address the above requirements?
2. Is transfer of Structure (WBS and activities), dates(schedule) and capacities possible from Primavera and PS and back. What are the issues encountered in such scenario?
3. What are the timelines for such solution?
Regards
Martin
Hi
As suggested, Iit is advisable to download SAP PS into MS project and then export the project to primavera and vice-versa.
However, please find below some info/link on third party softwares available in market for primavera integration:
http://www.sapprimavera.com/2007/06/01/sap-primavera-integration-technology-options/
Regards
Srikrishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Everybody
Awarded points to helpful answers/ clues
Martin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Virendra and Shrikrishna
But Does anybody has first hand experienc of using Impress or any other Primavera-PS integration tool? Are there any guiding factors ?
Regards
Martin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i would not recommend use of OPENPS
I suggest you look into SAP PS Primavera integration tools - Impress is the most commonly used
this will provide better intefacability then OPEN PS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Ahmed for a quick reply.
Before I start working in this direction, I would like to have more clarity.
1.Is transfer of Structure (WBS and activities), dates(schedule) and capacities possible from Primavera to MPX and then to SAP- PS and back. More Important is backward flow as well as there will be changes certainly in schedule by by management to be communicated back to contractor. What are the issues encountered in such scenario?
2. Are there any tentative timelines on this?
Regards
Martin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is somewhat similar to my current project...Here also, Contractor will provide project planning in Primavera and my client wants to upload it in SAP...What I have suggested is...instead of buying a third party software for PS-primavera integration..You can ask the contractor to provide the project planning in .MPX format(MS-project), which can be obtained from Primavera itself...then later use OPENPS(std tool available with SAP without any charges)...to upload the data from MS_project to SAP...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.