prt update through production orders

Former Member
0 Kudos

hi, i am planning to update the prt usage w/o assigning the prt in routing. i created prt with cat P. Assigned product for which we need to create prod order in the same view of prt. in prt data tab, maintained sapf02 for usage value formula field, control key (1), start and end ref as 01 & 04. measuring point and maintplan were assigned in the same screen. now i created prod order, released and done confirmation with c015. in ik17, i could not see the update for prt usage. pls advise any thing wrong, any setting missig.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

closed as no responses recdideved.