on 09-14-2009 1:47 PM
Dear PS consultants,
Last few months i struggling to settle the Projects. I dont know wht is the problem also. IS Project settlement required COPA? Strategies is required in the settlement process. any body has any inputs advice us.
Regards
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sukhveer Singh,
what is the necessaity to settle to gl account. A Customer project is a temporary Cost Object. If we want to settle to Cost Center it has a meaning, how can we sttle to G/L Account. what is the logic.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Is it required the COPA to settle the Customer Project.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Settlement depends upoon the type of Project.
If it is Investment Project (where Asset is created) it has to be settled on Asset.
For Customer project it can be settled on Cost center.
It depend upon your Configuration for Settelment Profile and Allocation Structure.
Regards,
Nitin Ghadge
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.