Hi Gurus,
Can you please tell me how i can convert planned order into production order in APO? How that production order will be transfer to ECC?
Regards
Rajib Pathak
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Rajib,
The following are required -->
1. Active Intergration Model for production orders in R/3 .
2. Distribution definition (T.Code /sapapo/cp1) in APO.
3. Retransfer settings (optional, read the F1 help here,before setting one) (T.code /sapapo/cp3)
Also make right setting for transfer for inhouse production in /sapapo/rrpcust1 in APO.
Then create a planned order and check the "Conversion indicator" in the product view (/sapapo/rrp3). or use transaction /sapapo/rrp7 to convert orders in mass.
Thanks,
Mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.