on 09-14-2009 12:47 PM
dear all
i have a problem, Suppose in the Scheduling agreement if there are x material giving different dates for delivery ,
eg : material delivery dates qty
X 10.10.2009 200
X 15.10.2009 100
the question is suppose if there are stock avialble in the storage location before the delviered dates the system should allow to do delivery say on 05.10.2009 . instead of throwing error msg. " tht the delviery can happen only on 10.10.2009" is it possible kindly tell me how to proceed on this
wailting for reply in anticipation
.
Hi there,
Manually it is possible to create delivery on 05.10.09. In VL01N, enter the shipping point, sales order & schedule line date 15.10.09 & create delivery. System will allow. Automatic delivery creattion is not possible for an earlier date. System will take only schedule line date in automatic delivery creation.
Regards,
Sivanand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
thanks for your reply , but my question is can i put my date 05.10.2009 and create a delivery or not, if i do the system is showing error msg tht " no scheduline due for delivery upto the selected date" as my client is saying i dont want to put the schedule date and execute. is it possible to put the the earlier date than the seleceted date and exceute , if so how
waiting for reply
thanks and regards
kumi
if the msg is showing up aftet giving 05.10.2009 then availabilty is not confirmed for that date . Uncheck the availbilty at the schedule line level in SPRO for schedule line category you using and try creating the delivery.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to 0VLP and select your item category for the delivery and execute.
Now in that just check the setting of the availckoff.
It should be blank.
So when ever you do the delivery it will again check the stock and create the delivery.
But for that purpose you need to go VL01N and create the delivery.
Regards
Raj.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi raj thanks for your reply,
i checked the avalch off is blank only... is there any other way i am still getting the same msg " no scheduline due for delivery up to tthe selected date" my client is asking i shouldnt put the correct schedule date and do the delivery in vlo1n, they system should allow me to put the earlier date and the delivery should happen , if there is stock available in the stroc location.. pls help me on this
waiting for reply in eagerly
kumi
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.