Assign Planning Plant for PM orders

I am working on the configuration of PM and need help to assign a Plant to be able to creat PM order.

Currently in my Dev, I have about 4 plants and ONLY 2 plants that allow the users to creat PM Orders and the other 2 are not yet assgned and I need to assign them as well.

Will Reward points!

Tim

replied

Also,

in SPRO, Under Enterprise Structure>Definition>Plant Maintenance-->Maintain Maintenance Planning Plant.

Here I think you can add the other plants.

Regards,

Rich Heilman

0 View this answer in context