Funds Precommitment - Open amount is not updated

Former Member
0 Kudos

Dear colleagues,

When we close Precommitment document, open amount in the Earmarked Funds document is not updated.

We had a similar problem with Earmarked Funds document and FI document which is solved using note 1376800.

Our component version is SAP ECC 6.0, release 600.

Can anyone help me with this problem?

Thanks and regards,

Tomislav

Accepted Solutions (0)

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Kudos

Hi Tomislav,

What happens if you run a report FMN5N (transaction)? Does system notify of missing line?

Regards,

Eli

Former Member
0 Kudos

Hi Eli,

Yes, we run FMN5N and nothing happened.

Document is updated, but not the open amounts.

Regards

Tomislav