WBS scheduling

Former Member
0 Kudos

Dear All

In Project my activity durtion is 12 hour or <24 but when i schedule the project then it will adjust the wbs basic date according to 24 hour, can any body tell me how wbs will show the exact time as per activity when i will schedule the project?

Thanks

Atif

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Atif,

Goto SPRO>Project System>Dates>Date Planning in WBS

select your WBS scheduling profile and uncheck the "adjust basic dates " indicator.

Regards!

Harsh