Dear All
In Project my activity durtion is 12 hour or <24 but when i schedule the project then it will adjust the wbs basic date according to 24 hour, can any body tell me how wbs will show the exact time as per activity when i will schedule the project?
Thanks
Atif
Dear Atif,
Goto SPRO>Project System>Dates>Date Planning in WBS
select your WBS scheduling profile and uncheck the "adjust basic dates " indicator.
Regards!
Harsh