Hi All ,
I have created project and assigned the logical component which includes 3 systems with DEV, Test and Prod roles .
When I define a Business Blueprint in SOLAR01 it opens by default a project with an "evaluation system" role.
My question is which one of the systems in my system landscape supposed to be an evaluation system, Dev , Test or Prod ?
What is the best practice ?
I know that is Evaluation system is designed for Business Blueprint phase , but what is really meaning ?
Cheers ,
Evgeny
Hi all,
I've had the same issue with regards to getting the error below when assigning transactions to a Blueprint business process.
"No system found for component and Evaluation system in the Project"
But I think I have solved it and seems pretty simple to change the system role from Evaluation System to any other that is relevant in your landscape.
Go to transaction SOLAR01 > Click on the first level of the Project Name (Under Business Blueprint Structure) to select the Project.
Click Business Blueprint in the Menu > System Role > Choose the relevant System Role (in my case Development)
Click Copy
This should replicate to all nodes and then you should be able to assign transaction to the business processes.
Quite strange and seems simple, I checked the Solution Directory, Solar Project Admin etc etc but couldn't find the solution until this which should work.
If not, there is a similar work around which also works.
Go to transaction SOLAR_PROJECT_ADMIN
System Landsacpe Tab
Systems subtab
Click System Role Assignment
Remove the Evaluation System (or all those not relevant to your Project and Logical Components)
Save Project
Go to SOLAR01 and it should reflect it in the Blueprint.
You can always go back to this and add the System Roles you removed and the Blueprint will reference the correct Role.
Hope this helps everyone,
-Rohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
That's right , but I would want to clarify my question .
I have physically 3 systems (DEV, TEST , PROD ) and I have assigned them to the logical component with proper roles
When I create a project I need to assign logical component to the project .
After , when I assign transaction and logical component to the business process (in solar01) I get the error" No system found for component and role Evaluation system in Project ". And that's , as I understand , because solar01 always opens by default the System Role " Evaluation System".
So that , my question is which one of my systems I am choosing to be (logically) an evaluation system ?
Cheers ,
Evgeny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Evgeny Fridlis ,
Even im also facing the same - But i dont have 3 sytem - i have only 1 system i.e PRD system and im facing the same problem in it. How you have came out from this situation. Please let me know - i have stuck up over here , its an production issue with importance. Do the needful. Thanks in advance.
Amrita
Evaluation System is not an SAP term but rather a generic term.
Evaluation System imply the step before Training System.
I would see this as a sandbox like defintion.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.