on 09-12-2009 4:20 AM
Hi Friends,
We are trying to change the MRP type of some materials from PD to a new MRP type ZD. ZD is a replica of PD (No Planning). Is there anything specific that should be taken care off while doing this change?
Please assist...
hi
You have to do this changes in ECC 6.0 for the relevant material master
Regards
G.Ganesh Kumar