We have recently completed a system refresh from our BI production system to our BI training system for the first time.
Our customer then wanted us to link our refreshed BI training system to our pre-production ECC system. After some initial issues setting up the connections between the two systems we finally got a successful test connection in RSA1 from our BI training system to our ECC pre-prod system. We had our BI functional team test, they told us that they do not see any of the infopackages and that transfer rules for loading hierarchies from our ECC pre-prod system are missing. Does anyone know how this could happen and what we can do to resolve/get the infopackages into our training system ?
We are on BI 7.0 and ECC 5.0
Solaris OS
Oracle DB
Thank you,
Steve
Hi Steve,
I would assume you deleted the sourcesystems, as adivised by the system copy note (886102). When you delete the sourcesystems, all its dependant objects are deleted too (like the infopackages, for example).
You can get them via transport, as suggested in the scenario B3, from that same note.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you run BDLS to covert the logical system name refering to ECC Prod to ECC Pre-prod after system copy
Or did you made a new connection with ECC Pre-prod.
Refer sapnote 0000886102
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.